ILAB facilitates opportunities for learning and reflection by publishing learnings documented in project evaluation reports. Lessons learned and promising practices found in these reports are presented here in a searchable database so that these valuable learnings may be considered in the development of new programming. To view the evaluation reports and other research from which these learnings are collected, please see our performance, monitoring and accountability page.
Filters
Evaluation Learnings Search Results
Showing 271 - 280 of 1191Project Title | Evaluation Type | Learning Type |
---|---|---|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description There is a need of continuous assessment of project strategies in view of a quickly shifting implementation situation. In particular, early adaptation to a changing institutional environment would be beneficial, e.g. for REST and Catch-Up activities. Hence, the possibility to rapidly devise strategies for reallocation of funds, and/or quickly acting on needs, such as the school feeding program and/or health insurance would be advantageous. Regardless of the decision taken (continue/discontinue Catch-Up program activities; allow/not allow project payment of the school feeding program and health insurance for beneficiaries), it is important to come to a solution quickly, so as not to encumber implementation and allow for new strategies to evolve as a response to the initial decision taken. Similarly, it is important that project-related research do not “hold up” project implementation. Often, research activities take longer time than initially expected, especially if organized from abroad, and if it needs lengthy rounds of review and clearance, etc. It should be noted that in most interviewees’ opinion, this project is characterized by good communication between all implementing partners (donor, host government, implementing partners, including home office of grantee), but interviewees also noted that the decision making processes for project related questions could have been faster. Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description Project implementation dates should take into account the local school year, to the extent possible. Rwanda, similar to much of Central and Southern Africa, is operating with an academic year matching the calendar year. Already at project conception, this could be taken into consideration to maximize project effectiveness. In this case, ceasing all project activities in September 2017 may not be the best way to proceed. Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description REACH-T is working at several levels, addressing the needs of several groups, including government and regional authorities as well as involving district and sector authorities. Also, it is working at school and community levels. The strategy is multiplying venues for awarenessraising and the likelihood of impact. Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description Use of mentors and community activists for awareness raising and monitoring of beneficiaries as well as of the child labor situation in the community through the CLMS. This is an effective way of raising awareness and also, through its reporting function, effectively involves local authorities in both the monitoring and child labor situation locally. _x000D_ Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description Community involvement in the selection of beneficiaries has led to services being provided to those who need it most. Through its selection mechanisms, the project has managed to involve the most disadvantaged as stakeholders and beneficiaries. The good practices of selection could be adopted in other projects, and is noteworthy. Paradoxically, the project’s success in this regard has also led to challenges, since the most destitute population is also the one for which project activities are at risk of being the least sustainable. The poverty level for many project beneficiaries is such that participation in saving activities, or in investment for the most basic income generating activities, is almost impossible. _x000D_ Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description The Child Labor Monitoring System and its associated ALERT mobile phone application is a good practice at many levels: it is an innovative technology with a lot of potential; it helps with tracking the work status of both beneficiaries and non-beneficiaries; it raises awareness among local officials and community members; and it is not limited to school hours but can potentially cover weekends, holidays and after-school hours. However, as with all new technology, it also faces some challenges: its geographic coverage is limited, and the strategy for expansion and turnover to Government are still a challenge (which government level, and who specifically, would be able to react to the reports; what is the official status of the community activists; who, in addition to key stakeholders, should have access to the reports). Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description Research activities: The project is involved in/has commissioned multiple research activities and has already completed several studies that are documenting the needs of children in tea growing areas of Rwanda. Click here to access the report |
|
|
Protecting the Working Conditions of People/ Proteje Kondisyon Travay Moun (PWOKONTRAM) Learning Description Hiring project case workers living in the same communities as project beneficiaries as a means to establish a close relationship with beneficiaries and ensure regular follow-up on their education and work activities. Click here to access the report |
|
|
Protecting the Working Conditions of People/ Proteje Kondisyon Travay Moun (PWOKONTRAM) Learning Description Quarterly planning and evaluation meetings between grantee Catholic Relief Services and implementing partners as a means to improve performance and build team capacities. Click here to access the report |
|
|
Protecting the Working Conditions of People/ Proteje Kondisyon Travay Moun (PWOKONTRAM) Learning Description Organizing savings and loans groups (MUSO, or Mutual Solidarity Groups) among participants as a sustainable livelihoods strategy. Click here to access the report |
|
|
Project Title | Evaluation Type | Learning Type |
---|---|---|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description There is a need of continuous assessment of project strategies in view of a quickly shifting implementation situation. In particular, early adaptation to a changing institutional environment would be beneficial, e.g. for REST and Catch-Up activities. Hence, the possibility to rapidly devise strategies for reallocation of funds, and/or quickly acting on needs, such as the school feeding program and/or health insurance would be advantageous. Regardless of the decision taken (continue/discontinue Catch-Up program activities; allow/not allow project payment of the school feeding program and health insurance for beneficiaries), it is important to come to a solution quickly, so as not to encumber implementation and allow for new strategies to evolve as a response to the initial decision taken. Similarly, it is important that project-related research do not “hold up” project implementation. Often, research activities take longer time than initially expected, especially if organized from abroad, and if it needs lengthy rounds of review and clearance, etc. It should be noted that in most interviewees’ opinion, this project is characterized by good communication between all implementing partners (donor, host government, implementing partners, including home office of grantee), but interviewees also noted that the decision making processes for project related questions could have been faster. Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description Project implementation dates should take into account the local school year, to the extent possible. Rwanda, similar to much of Central and Southern Africa, is operating with an academic year matching the calendar year. Already at project conception, this could be taken into consideration to maximize project effectiveness. In this case, ceasing all project activities in September 2017 may not be the best way to proceed. Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description REACH-T is working at several levels, addressing the needs of several groups, including government and regional authorities as well as involving district and sector authorities. Also, it is working at school and community levels. The strategy is multiplying venues for awarenessraising and the likelihood of impact. Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description Use of mentors and community activists for awareness raising and monitoring of beneficiaries as well as of the child labor situation in the community through the CLMS. This is an effective way of raising awareness and also, through its reporting function, effectively involves local authorities in both the monitoring and child labor situation locally. _x000D_ Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description Community involvement in the selection of beneficiaries has led to services being provided to those who need it most. Through its selection mechanisms, the project has managed to involve the most disadvantaged as stakeholders and beneficiaries. The good practices of selection could be adopted in other projects, and is noteworthy. Paradoxically, the project’s success in this regard has also led to challenges, since the most destitute population is also the one for which project activities are at risk of being the least sustainable. The poverty level for many project beneficiaries is such that participation in saving activities, or in investment for the most basic income generating activities, is almost impossible. _x000D_ Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description The Child Labor Monitoring System and its associated ALERT mobile phone application is a good practice at many levels: it is an innovative technology with a lot of potential; it helps with tracking the work status of both beneficiaries and non-beneficiaries; it raises awareness among local officials and community members; and it is not limited to school hours but can potentially cover weekends, holidays and after-school hours. However, as with all new technology, it also faces some challenges: its geographic coverage is limited, and the strategy for expansion and turnover to Government are still a challenge (which government level, and who specifically, would be able to react to the reports; what is the official status of the community activists; who, in addition to key stakeholders, should have access to the reports). Click here to access the report |
|
|
Rwanda Education Alternatives for Children in Tea-Growing Areas (REACH-T) Learning Description Research activities: The project is involved in/has commissioned multiple research activities and has already completed several studies that are documenting the needs of children in tea growing areas of Rwanda. Click here to access the report |
|
|
Protecting the Working Conditions of People/ Proteje Kondisyon Travay Moun (PWOKONTRAM) Learning Description Hiring project case workers living in the same communities as project beneficiaries as a means to establish a close relationship with beneficiaries and ensure regular follow-up on their education and work activities. Click here to access the report |
|
|
Protecting the Working Conditions of People/ Proteje Kondisyon Travay Moun (PWOKONTRAM) Learning Description Quarterly planning and evaluation meetings between grantee Catholic Relief Services and implementing partners as a means to improve performance and build team capacities. Click here to access the report |
|
|
Protecting the Working Conditions of People/ Proteje Kondisyon Travay Moun (PWOKONTRAM) Learning Description Organizing savings and loans groups (MUSO, or Mutual Solidarity Groups) among participants as a sustainable livelihoods strategy. Click here to access the report |
|
|